Woods Hole Ferry Terminal Reconstruction Project

Posted: June 14, 2019

To report concerns about construction or environmental issues concerning the Woods Hole Terminal Reconstruction Project. Please call 508-289-4419 to be connected with either Bill Cloutier or another Authority staff member, should you have a concern that needs immediate attention. As always, you can also email Bill at bcloutier@steamshipauthority.com during work hours or call his office line 508-548-5011, ext. 429.

Steamship Authority Board to meet on revised terminal design options

The Steamship Authority’s Board will hold a special meeting next week to review the public feedback received to date and to vote on a proposed framework for revised schematic design phase services by the Authority’s architect on the project, BIA.studio.

The meeting will be at 5:30 p.m. Tuesday, June 18, 2019 in the auditorium of Falmouth High School, 874 Gifford Street, Falmouth. The terminal design is the only item on the agenda.

Vineyard residents taking either the 3:45 p.m. boat from Oak Bluffs or the 4:05 p.m. freight boat from Vineyard Haven may board a specially designated Authority bus, which will transport you from the Woods Hole terminal to the high school. Buses will be available at the end of the night to transport island residents to Woods Hole for the next available departure.

Nantucket residents wishing to arrange transportation to or from the Hyannis terminal should contact Communications Director Sean Driscoll at sdriscoll@steamshipauthority.com as soon as possible.

Below are links to a staff summary on the proposed framework for the revised schematic design phase services as well as a report from the Woods Hole Group on the site. 

Staff Summary #GM-723: Request for Authorization to Develop a Revised Woods Hole Terminal Building Design

Woods Hole Group final report 

Steamship Authority releases revised terminal design options

At its March 19, 2019 Board meeting, the Woods Hole, Martha's Vineyard and Nantucket Steamship Authority released three design options under considerating for its Woods Hole terminal building. 

View and download the presentation here: March 19, 2019 Woods Hole Terminal presentation on design alternatives

View and download the March 28, 2019 presentation at Falmouth High School Audiorium here: Woods Hole Terminal Building – Design Update.

View and download the Steamship Authority's responses to public comments received followign the October design presentations here: Responses to public comments.

June 14, 2019 Update

This week, Jay Cashman Inc. continued demobilizing operations, and the remaining barge will be departing from the site by the end of the day on Saturday, June 15, 2019. Meanwhile, remaining work for the electrical, plumbing, and fuel systems was performed to ensure the slip is fully operational. Final work and site cleaning will continue into next week to support the startup of operations in the slip, including final testing of the fuel system. Installation of the ticket scanner system and telecommunications equipment in the attendant booth has also begun.

Robert B. Our Company is also continuing work on the sewer pump out system that we expect to be operational by the end of June.

 

October 16, 2018 Presentation

To view recent images of the Woods Hole Terminal Reconstruction project, please click on the links below. These images were presented at the Steamship's recent board meeting on October 16, 2018.

10.16.18Presentation1

10.16.18Presentation2

October 9 & 10, 2018 Presentation to Public

The link below provide an update on the preliminary design of the new terminal building that will be located at the site. Architecture firm BIA.studio (formerly Bertaux + Iwerks) and SSA Managers presented this update to the public in Falmouth and in Vineyard Haven.

Public Presentation October 2018

September 14, 2018 update on new terminal design:

The links below provide an update on the preliminary design of the new terminal building that will be located at the site. Architecture firm BIA.studio (formerly Bertaux + Iwerks) made presentations in August 2018 to the Port Council and Authority Board on the latest version of the terminal design.

Temporary Passenger Platform Canopy
Site Plan
Building Plans
Elevations 1
Elevations 2
Seasonal Shading at Plaza
Design Development
Circulation Plan - Entering
Circulation Plan - Exiting

Related documents

Chapter 91 license

Chapter 91 license - recommended final decision

Falmouth Conservation Commission Order of Conditions

ENF Certificate

Environmental Notification Form (WARNING: large file)

2014 Feasbility Study 

Phases 2 through 4 (Waterside Work) of the Terminal Reconstruction Project

At a special Board meeting on December 5, 2017, the SSA’s Board awarded the marine construction contract for the waterside work that will be completed in Phases 2 through 4 of the project to Jay Cashman, Inc., of Quincy, Massachusetts, for the Total Contract Price of $43,143,280.  As a result, we have now begun Phase 2 of our multi-year, phased construction project that will result in the complete reconstruction of our Woods Hole ferry terminal over the next six years.

The overall project entails the phased demolition of all of the existing waterfront structures that include the current three ferry slips and supporting utilities to be replaced with three new ferry slips, two passenger loading piers, and comprehensive utility and stormwater management improvements. Following the waterside construction, landside improvements include site re-grading, a new ferry terminal building and equipment storage building, bus berths and overall reconstruction of site utilities and vehicle accommodations.

Because we want to minimize the potential impact of the project’s construction activities on our own operations and adjacent property owners and local businesses, most of the onsite work will be accomplished in phases during “off-seasons” that will run from early September through mid-May each year.  Only one slip will be reconstructed at a time to ensure that we will always have two slips available to maintain our regular ferry service.  During each summer season, we will also have the third slip available so that we can berth three vessels at the terminal.  All construction activity at the terminal site will effectively cease during each summer season except for limited activity that does not have a material impact on either our operations or the Woods Hole community.

The first slip that will be reconstructed is Slip 3, which is the slip closest to the village and next to the Naushon Trust dock.  During Phase 2 of the project, it will be repositioned southwest so that its transfer bridge is located pretty much where the northwest side of the current ticket office is.  To accomplish this, we first need to reroute the power service for the slip, which comes out of the existing ticket office, and then demolish the existing ticket office and excavate the western portion of the wharf.  We will also remove the existing passenger loading/unloading systems on the wharf to the area between existing Slips 1 and 2, where we will construct a temporary passenger loading/unloading system next spring.

After the existing terminal building is demolished, we will begin excavating the building’s foundation and a portion of the wharf to allow for the docking of our ferries at that location.  By the commencement of the 2018 summer season, we expect to have excavated the building’s foundation but not to have had sufficient time to complete the excavation of the wharf.  The excavation will then continue next fall and all of the remaining work in Phase 2 of the project to construct the new Slip 3 will be completed during the two following off-seasons (September 2018 through May 2019 and September 2019 through May 2020).

You can click on the links below to see the following documents relating to these phases of the project: