Current Promotion

Current Promotion

Island Alpaca

Come visit and learn all about Martha's Vineyard alpacas.

http://www.islandalpaca.com/

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

Island Alpaca

Come visit and learn all about Martha's Vineyard alpacas.

http://www.islandalpaca.com/

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

Woods Hole Terminal Reconstruction Project

September 21, 2018 Update

This week, four barges arrived on site to start the marine work. Jay Cashman Inc. spent most of the week unpacking and setting up its cranes. Lawrence Lynch finished removing the preload material last Friday (September 14, 2018) and removed the remaining concrete blocks this week.

Next week, Cashman hopes to get underway with the marine work. They will pre-trench the wharf where the new sheet piles will be driven and will also start the demolition of the old sheet pile walls. The work should be ramping up pretty quickly now that all the equipment has arrived.

September 14, 2018 Update on design of new terminal:

The links below provide an update on the preliminary design of the new terminal building that will be located at the site. Architecture firm BIA.studio (formerly Bertaux + Iwerks) made presentations in August 2018 to the Port Council and Authority Board on the latest version of the terminal design.

Temporary Passenger Platform Canopy
Site Plan
Building Plans
Elevations 1
Elevations 2
Seasonal Shading at Plaza
Design Development
Circulation Plan - Entering
Circulation Plan - Exiting

In late September or October, the Steamship Authority will schedule community presentations on the design.

Phases 2 through 4 (Waterside Work) of the Terminal Reconstruction Project

At a special Board meeting on December 5, 2017, the SSA’s Board awarded the marine construction contract for the waterside work that will be completed in Phases 2 through 4 of the project to Jay Cashman, Inc., of Quincy, Massachusetts, for the Total Contract Price of $43,143,280.  As a result, we have now begun Phase 2 of our multi-year, phased construction project that will result in the complete reconstruction of our Woods Hole ferry terminal over the next six years.

The overall project entails the phased demolition of all of the existing waterfront structures that include the current three ferry slips and supporting utilities to be replaced with three new ferry slips, two passenger loading piers, and comprehensive utility and stormwater management improvements. Following the waterside construction, landside improvements include site re-grading, a new ferry terminal building and equipment storage building, bus berths and overall reconstruction of site utilities and vehicle accommodations.

Because we want to minimize the potential impact of the project’s construction activities on our own operations and adjacent property owners and local businesses, most of the onsite work will be accomplished in phases during “off-seasons” that will run from early September through mid-May each year.  Only one slip will be reconstructed at a time to ensure that we will always have two slips available to maintain our regular ferry service.  During each summer season, we will also have the third slip available so that we can berth three vessels at the terminal.  All construction activity at the terminal site will effectively cease during each summer season except for limited activity that does not have a material impact on either our operations or the Woods Hole community.

The first slip that will be reconstructed is Slip 3, which is the slip closest to the village and next to the Naushon Trust dock.  During Phase 2 of the project, it will be repositioned southwest so that its transfer bridge is located pretty much where the northwest side of the current ticket office is.  To accomplish this, we first need to reroute the power service for the slip, which comes out of the existing ticket office, and then demolish the existing ticket office and excavate the western portion of the wharf.  We will also remove the existing passenger loading/unloading systems on the wharf to the area between existing Slips 1 and 2, where we will construct a temporary passenger loading/unloading system next spring.

After the existing terminal building is demolished, we will begin excavating the building’s foundation and a portion of the wharf to allow for the docking of our ferries at that location.  By the commencement of the 2018 summer season, we expect to have excavated the building’s foundation but not to have had sufficient time to complete the excavation of the wharf.  The excavation will then continue next fall and all of the remaining work in Phase 2 of the project to construct the new Slip 3 will be completed during the two following off-seasons (September 2018 through May 2019 and September 2019 through May 2020).

You can click on the links below to see the following documents relating to these phases of the project:

  • A satellite photograph of the terminal prior to construction, and then a feasibility phase drawing of the site plan for the reconstructed terminal superimposed over the photograph.  Satellite Photograph & Site Plan

  • Drawings showing what demolition and construction work is going to be accomplished during each phase of the Waterside Work (Phases 2 through 4).  Phase 2  Phase 3  Phase 4

  • Drawings of the three reconstructed ferry slips, including a drawing showing their different elevations.  Ferry Slip Drawings

  • Renderings that show different perspectives of the three reconstructed ferry slips.  Ferry Slip Perspective Renderings

  • A July 2017 schematic design phase drawing of the site plan for the reconstructed terminal.  Schematic Design Phase Site Plan