Current Promotion

Current Promotion

Current Promotion

Current Promotion

Current Promotion

Current Promotion

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

American Auto Transporters

Nationwide transport, BBB A+, Guaranteed pick up date, on time delivery

shipcar.com

Woods Hole Terminal Reconstruction Project

To receive weekly email updates about the terminal reconstruction project, please visit our new eNews provider, GovDelivery, and subscibe! Click here to sign up

To report concerns about construction or environmental issues concerning the Woods Hole Terminal Reconstruction Project. Please call 508-289-4419 to be connected with either Bill Cloutier or another Authority staff member, should you have a concern that needs immediate attention. As always, you can also email Bill at bcloutier@steamshipauthority.com or call his office during work hours at 508-548-5011, ext. 429.

Week ending December 2, 2022

THIS WEEK, Lawrence-Lynch Corp. finished the remaining water utilities and drainage scope in the phase 5B work site.

NEXT WEEK, Lawrence-Lynch will begin raising the grade and all drainage and electrical structures within the Phase 5B work site to final elevations. Cullen Electric is also scheduled to begin installing site electrical and communications utilities. Lawrence-Lynch is grading all areas in front of Slip No. 1 for paving; Phase 5C should start the week of December 12, 2022.

Week ending November 18, 2022

THIS WEEK, Lawrence-Lynch Corp. finished the installation of the stormwater drainage in the work site.

NEXT WEEK, Lawrence-Lynch will connect the water line in the Phase 5B work site with the Town of Falmouth’s water line on Cowdry Road. The work week will be short because of the Thanksgiving holiday.

Week ending November 11, 2022

THIS WEEK, Lawrence-Lynch Corp. continued to install drainage piping and stormwater structures in the work site. The work site is too congested for Cullen Electric to install the required electrical conduits. No work will occur on Friday due to the Veterans Day holiday. 

NEXT WEEK, Lawrence-Lynch will continue installing stormwater structures in the work zone and in the employee parking lot. Lawrence-Lynch will start installing the water line in the work site. A fencing contractor is scheduled to mobilize and extend the fence that is fastened to the retaining wall at the property line.

Week ending November 4, 2022

THIS WEEK, Lawrence-Lynch Corp. set up the dewatering equipment to dewater the holes for the stormwater structures. They installed the first structure in the Phase 5B work site. The concrete subcontractor completed the retaining wall at the southern property line. Cullen Electric was not able to trench and install electrical conduits as previously planned because of the other activities at the worksite.

NEXT WEEK, Lawrence-Lynch will continue installing stormwater structures in the work zone. A fencing contractor is schedule to mobilize and extend the fence that is fastened to the retaining wall at the property line. 

Phase 5 landside work 

The scope of work for this phase focus on preparing the site for the building construction. The electricians will set up a temporary switchgear building in the employee lot so power can be moved from the freight shed. Lawrence Lynch will be raising the base elevation approximately 5 feet to satisfy the flood plain requirements, and they will be installing new stormwater piping for the back side of the property. This piping will connect with the stormwater piping that was installed as part of the marine contract. Raising the site elevation is complicated logistically because the site must stay in operation during the construction. We plan to complete the elevation work by moving the construction work zone six different times. This will allow vehicle access to at least two vessel slips at all time and continue to have staging available at the site.

 

Click here to download maps of the six subphases of the project.

Click here for videos of the Schematic Design and Design Development public engagement sessions.

January 19, 2022 Community Engagement Session Presentation  

November 4, 2021 Landside Community Update presentation 

July 7, 2021 Landside Design Presentation

Landside Design Community Forum (updated 3/23/2021)


Related project documents

Chapter 91 license

Chapter 91 license - recommended final decision

Falmouth Conservation Commission Order of Conditions

ENF Certificate

Environmental Notification Form (WARNING: large file)

2014 Feasibility Study